Deploying a node
The Deploy screen allows you to change the settings for the node you are deploying. You can change the:
-
Installation options.
-
Reboot options.
-
iLO Repository options (Gen10 iLO 5, Windows, and Linux nodes only).
-
Components to deploy and configure components from the Baseline Library screen.
-
If you run SUM on a virtual machine running a supported operating system, do not deploy updates to the localhost system. Deploy updates to remote nodes only.
-
When SUM activates the Deploy button, do not manually update or downgrade a component that SUM manages. Updating the component manually will cause SUM to skip the component and report an error.
- From the Nodes screen, select a node to update, and then select Actions > Review/Deploy.
-
Select the
Installation Options tab to change:
-
Downgrade and Rewrite options.
- Upgrade Firmware and Software.
-
Upgrades firmware and software components.
- Upgrade Firmware.
-
Upgrades only firmware components.
- Upgrade Software.
-
Upgrades only software components.
- Downgrade and Rewrite both
-
Upgrades, downgrades, and rewrites firmware and software components.
- Downgrade and Rewrite Firmware
-
Upgrades, downgrades, and rewrites only firmware components.
- Downgrade and Rewrite Software
-
Upgrades, downgrades, and rewrites only software components.
- Downgrade both
-
Upgrades and downgrades firmware and software components.
- Downgrade Firmware
-
Upgrades and downgrades only firmware components.
- Downgrade Software
-
Upgrades and downgrades only software components.
- Rewrite both.
-
Upgrades and rewrites firmware and software components.
- Rewrite Firmware.
-
Upgrades and rewrites only firmware components.
- Rewrite Software.
-
Upgrades and rewrites only software components.
-
Verbose logging or normal logging.
-
Skip Components with Dependency Failures
-
Select whether to clean up temporary files after deployment.
-
Select whether to clean up debug logs and temporary files after deployment.
NOTE:If an OA is in FIPS mode, SUM does not support downgrading or rewriting firmware. SUM displays a message and turns off the downgrade and rewrite options.
-
-
On the
Reboot Options tab, select the following:
-
Select a system reboot option:
Never
,If needed
,Always
. - Enter the number of minutes SUM delays before rebooting the node. Select 1-60 minutes.
- Enter a reboot message, up to 255 characters, to display.
NOTE:The reboot_message cli parameter is not functional in the case of SLES12 OS because the SLES12 OS image has a constraint that does not permit executing the parameter as a cli command.
-
Select a system reboot option:
-
Gen10 iLO 5 Windows and Linux nodes only: To manage the iLO Repository, select the
iLO Repository Options tab.
-
To upload selected components to the iLO Repository and create an install set, select
Save Components as an Install set on iLO Repository.
SUM automatically creates a default name and description, but you can edit the name and description for the install set. You can use this install set to roll back the server components at a future time. The name and description are limited to 63 characters, and the only special characters are
-
and_
. -
Select one of the following:
-
SUM manages iLO Repository space: SUM automatically creates space on the iLO Repository if necessary. SUM deletes:
-
Unreferenced components first.
-
Deletes the oldest install set. iLO Repository can save a maximum eight install sets.
-
-
Manually manage iLO Repository space: You select the install sets or unreferenced components to delete to free up iLO Repository space.
-
-
To upload selected components to the iLO Repository and create an install set, select
Save Components as an Install set on iLO Repository.
SUM automatically creates a default name and description, but you can edit the name and description for the install set. You can use this install set to roll back the server components at a future time. The name and description are limited to 63 characters, and the only special characters are
-
Select the components from the
Baseline and
Additional Packages tabs that you want to deploy.
If you are deploying updates to an iLO5 node, SUM automatically selects components based on the operating system that is running on the node. If the node is off, SUM selects components based on the operating system running SUM.
NOTE:Gen10 iLO 5 nodes require all components include a component signature file. If the signature file is missing, SUM disables the Deploy button. Deselect components without signature files to deploy other updates.
-
Click
Deploy.
SUM verifies any changes that you made are valid and then begins deploying components.
NOTE:
To begin the deployment, all dependency issues must be resolved, or clear the component so it does not install.
-
In the General section of the Node screen, click
View log for the node, and then click
View log for the component you installed to view the details of the installation.
NOTE:
On the node page, click the Live Log button to view the deployment status while SUM is deploying updates.